Information on setting up by ELEKTROTIM S.A. a reserve for contractual penalties to the contract concluded with the Military Management of Infrastructure with its seat in Poznań.

Current report number:

4/2017

Date:

27.01.2017

The Management Board of ELEKTROTIM S.A. informs that on 26.01.2017 the Company received an accounting note from the Military Management of Infrastructure with its seat in Poznań (herein also referred to as the Ordering Party) in the amount of PLN 1,956,136.65 for charging ELEKTROTIM S.A. with “contractual penalties for delay in repairing defects and faults discovered during the technical or final commissioning or defects discovered during the statutory warranty and warranty (date of note: 19.01.2017).