ELEKTROTIM S.A. with its registered office in Wrocław hereby informs that on 13 August 2026 it received information on the selection of ELEKTROTIM S.A.’s offer as the most advantageous in the proceedings conducted by PGE Energetyka Kolejowa Operator Sp. z o.o. entitled: “Construction of the 15 kV Traction Substation PT Radość along with technical infrastructure, 15 kV supply lines, supply cables, return cables and disconnector control cables, under the ‘design and build’ formula”.
The value of the offer submitted by ELEKTROTIM S.A. is PLN 17,752,300.00 net; PLN 21,835,329.00 gross.